Henvey Inlet Wind (HIW)– Construction Update - Construction Summary #1 - August to November 2017

For this reporting period (Aug-Oct) CER had employed 28 First Nations employees out of a total workforce on site of 93 Employees, this represents 30% of the overall workforce for CER.

For this reporting period (Aug-Oct) AECOM had has hired 13 First Nations residents in total.

These include 2 Qualified Biologists and 11 Environmental Monitors. The majority of the employees are residents of the three local First Nations, including 8 from Henvey Inlet, 1 from Magnetawan, 2 from Shawanaga and 2 from other First Nations.

For proposed work scheduled dates CLICK HERE to read the full report.